Welcome to our April 2026 Compliance Update.

Share this article

Dear Valued Partners, 

As regulatory requirements continue to evolve across the schemes, it is important to remain up to date and ensure your processes align with the latest program rules. Below is a summary of key updates and actions required for this month. 

1. VEU Residential Activities (1, 3 & 6) – Revised Evidence Requirements (Update 15 April 2026) 

Following the program update released on 15 April 2026, the Essential Services Commission has revised the recently introduced record-keeping requirements for water heating and space heating and cooling activities. 

What Has Changed 

The following previously introduced photographic evidence requirements have now been deferred and removed from the Activity Guide: 

  • Main switchboard before installation 
  • Main switchboard after installation (cover removed) 
  • Installed circuit showing amperage rating 
  • Main switch showing amperage rating 
  • Installation wiring showing type and size (where visible) 

What Remains in Effect  

The following requirements continue to apply: 

  • Existing product(s) before upgrade, in situ and connected to gas or electricity supply 
  • Installed product(s) after installation, including full wall and surrounding environment (indoor & outdoor units) 


We expect our loyal partners to take note of these changes and/or should you have any questions, feel free to reach out to our compliance team.  

2. VEU Commercial Water Heating (Activity 44) 

  • A minimum co-payment of $10,000 (incl. GST) is required per installed product 

What You Need to Do: 

  • Ensure invoicing and customer payment processes reflect this requirement 
  • Co-payment must be collected and evidenced in line with program rules 

Effective Date: 

31 March 2026 

3. VEU C&I Solar PV – Training & Record Keeping Updates (Effective 24 March 2026) 

Training & Competency Requirements 

  • All installers and on-site workers must hold a current construction induction card (White Card) 
  • Workers with superseded units of competency remain compliant if they hold a valid White Card 
  • White Cards issued in other Australian jurisdictions are accepted 

Record-Keeping & Activity Date Requirements 

  • Evidence of DNSP must be a Negotiated Connection Contract include a post-installation validation/output document 
  • The document must clearly include a post installation validation / output and show the date of DNSP validation/approval 

Activity Date Definition: 

  • The activity (implementation) date is the DNSP ‘Network Commissioning Test Approval’ date, as stated in the DNSP completion letter or email 

For partners participating in C&I Solar PV, we encourage you to contact your relevant Project Coordinator for further guidance: 

These updates are critical to maintaining compliance and avoiding delays in certificate creation. Please ensure full implementation within the required timeframes. 

4. STC Battery Installations – Photo Evidence Requirements (Reminder) 

A reminder that as of 1 March 2026, all installers must take clear, geo-tagged and time-stamped photographs of critical labelling for every solar battery installation. 

This requirement is in addition to existing installer on-site verification photos, including evidence of the installer being present during the main stages of installation. 

Requirements: 

  • Ensure all installations include clear photo evidence of critical labelling and system identification 
  • All on-site evidence must be collected and retained as part of compliance documentation 

Compliance Requirement: 

  • This obligation is legislated under Regulation 20ACA(12)(h)(iii) of the Renewable Energy (Electricity) Regulations 2001 

Important: 

Failure to comply may result in failed STC claims and potential compliance action 

5. Battery Rebates are changing from 1 May 2026 

From 1 May the STC factor will taper according to the amount of capacity installed: 

  • From 0 kWh up to 14 kWh (inclusive): STC factor applied at 100% 
  • Every kWh greater than 14 and up to 28 kWh (inclusive): STC factor applied at 60% 
  • Every kWh greater than 28 and up to 50 kWh (inclusive): STC factor applied at 15%. 

Keep in mind that STCs are calculated based on the usable capacity of your battery. 

  • Only the first 50kWh of usable capacity are eligible for STCs. 
  • Some STC calculation examples below: 
Current From 1 May 
10kWh system 
(100% x 8.4) 
Total 84 STCs 
* 10 kWh (100% x 6.8) 
Total 68 STCs 
20kWh system 
(100% x 8.4) 
Total 168 STCs 
* First 14kWh (100% x 6.8) = 95.20  
* Remaining 6 kWh (60% x 6.8) = 24.48 
Total 119 STCs 
30kWh system 
(100% x 8.4) 
Total 252 STCs 
* First 14kWh (100% x 6.8) = 95.20 
* Second 14 kWh (60% x 6.8) = 57.12 
* Remaining 2 kWh (15% x 6.8) = 2.04 
Total 154 STCs 

6. NSW ESS – CCEW Process Update (Effective 1 July 2026) 

Building Commission NSW (BCNSW) will introduce the following changes: 

  • Mandatory submission of CCEW forms via the eCert portal 
  • Signed CCEWs will no longer be required 

Important: 

  • CCEWs must continue to be supported by sufficient evidence, including: 
  • Installer declarations 
  • Commissioning reports 

Further guidance will be provided as requirements are refined.

Reminder: Vintage 2025 VEEC Claims – Deadline Approaching 

Please note that the cut-off date for all 2025 Vintage submissions to Northmore Gordon is Friday, 1 May 2026. 

Partners are strongly encouraged to ensure all required documentation is finalised and submitted well ahead of the deadline to avoid missing this final processing window. 

Closing remarks 

Staying on top of regulatory changes and maintaining strong compliance practices is essential to ensuring the integrity of the schemes and the smooth processing of certificates. 

We appreciate your continued cooperation and commitment to compliance. 

For further information or clarification, please contact our Compliance Team via [email protected]

Kind regards, 
Northmore Gordon Compliance Team

You may also like:

Latest Updates