Northmore Gordon worked closely with a Singapore- based parts manufacturer over 2021 to complete an Energy Efficiency Opportunities Assessment as required by Singapore’s National Environment Agency (NEA). The complex requirements of the Program were fully met and the report submitted on time. In addition, NG identified practical energy saving opportunities that are now being implemented.
The Client
The Client has been established in Singapore for many years, with several large manufacturing operations. The operation involves high-precision parts machining, custom treatment, finishing, and final inspection. It is supported by utilities including compressed air, air conditioning and large chiller systems, centralised lubrication systems, and cooling towers.
The Project
To meet the requirements of the Energy Conservation Act, Singapore sites that use over 54 TJ per annum must undertake an Energy Efficiency Opportunity Assessment.
The upgrades recommended included compressed air efficiency, shutting off unnecessary operation of equipment, and more efficient cooling for the machine-centre oil cooling system.
Key Facts
- EEOA-RC completed in line with regulation
- Annual Savings Estimates
- Energy: 1,900 MWh
- Carbon Abatement: 780 tCO2e
- OPEX: ~$180,000
- Project Details
- CAPEX: ~$460,000
- Payback: ~2.5 years
Challenges
- Competitive pressures to provide high quality service whilst minimising operating costs
- Energy bills represent a substantial cost the operations
- There are global targets for energy and water efficiency
- Ageing equipment and production pressures mean savings measures cannot impact reliability
Additional Benefits
- More stable air pressure is expected
- More stable operating temperatures
- Lower maintenance costs on pumps through reduced running hours.
Our Role
Northmore Gordon worked very hard to complete the work to the standard
required by the NEA in the timeframe. This included working through the difficulties of restrictions that occurred in 2020 due to
Covid lockdowns. The work included installing temporary metering, reading of on-site meters, development of a detailed energy balance, analysis of the data, identification of energy efficiency opportunities in conjunction with the Client, completion of the NEA’s report template, and achieving sign-off by the Client stakeholders.